This state-of-the-art facility will span 37,500 square feet, with 36,000 square feet dedicated to hangar space and 1,500 square feet of office accommodations.

  • Our vertically integrated approach leverages Tetra Development’s partnership with Tetra Steel Worx, ensuring seamless coordination of structural engineering, steel fabrication, and erection.

     

  • This proposal outlines our construction methodology, timeline, and detailed cost breakdown, demonstrating our commitment to delivering exceptional value through multi-craft accountability and accelerated construction processes.

Hangar Dimensions & Specifications

Office Accommodations

1,500 square feet of modern office space integrated into the facility, featuring climate-controlled workstations, conference areas, and technical planning rooms to support maintenance
operations.

Main Hangar Space

36,000 square feet of clear-span hangar space designed to accommodate multiple aircraft with a 30-foot clear height and 180-foot door clearance width.

Hangar Dimensions & Specifications

The comprehensive site plan illustrates the strategic positioning of the 37,500 square foot OMNI Air Transport Maintenance Hangar adjacent to American Airlines Hangar 80.

  • This carefully designed layout optimizes aircraft movement patterns, integrates necessary infrastructure connections, and provides efficient access to taxiways X and Runway Y

  • The plan demonstrates our thoughtful approach to spatial organization, ensuring both operational efficiency and compliance with aviation facility requirements.

Project Overview
and Specifications

Facility Specifications

  • Total Facility: 37,500 sq ft
  • Hangar Space: 36,000 sq ft
  • 180’x30′ Hangar Door Opening
  • Office Space: 1,500 sq ft
  • Construction Timeline: 10-14 months

Key Features

  • Pre-Engineered Metal Building (PEMB)
  • Custom Hangar Doors
  • Pre-Action Fire Suppression System
  • Modern Office Facilities
  • Complete Site Development

Financial Highlights

  • Total Project Cost: $6,031,620
  • Cost Per Square Foot: $160.84
  • TIF Available: 1% of project cost annually for 20 years
  • NMTC possible at 20% of cost basis
  • Longterm lease option at $16 psf